Are you doing release retrospectives?
Last Post 25 Feb 2013 04:58 AM by Sanjay Saini. 3 Replies.
  •  
  •  
  •  
  •  
  •  
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Author Messages
Fredrik Vestin
New Member
New Member
Posts:60
Fredrik Vestin

--
14 Feb 2013 01:43 AM
    And if so, how are they conducted?

    Thanks
    Fredrik
    Chee-Hong Hsia
    New Member
    New Member
    Posts:61
    Chee-Hong Hsia

    --
    15 Feb 2013 07:23 AM
    What's a Release Retrospective? :-)

    Fredrik Vestin
    New Member
    New Member
    Posts:60
    Fredrik Vestin

    --
    22 Feb 2013 05:01 AM
    Oh, sorry for not replying sooner. My inbox is a mess.
    I know some organisations have these kind of retros. The idea is to evaluate an entire release (not just a sprint) which can span multiple sprints. Although not formally a part of scrum I think it can be good to take a step back and try to look at the big picture. Sprint retros can be pretty narrow in context. Some invite stakeholders, management etc. and evaluate the collaboration in the entire organisation. If anyone has these kinds of retros I'd like to hear your experience. How are they conducted, are they valuable etc.

    Thanks
    Fredrik
    Sanjay Saini
    New Member
    New Member
    Posts:81
    Sanjay Saini

    --
    25 Feb 2013 04:58 AM

    We did it once and it was done by each individual group separately i.e. scrum teams, scrum master, POs and Program management team. The each individual group's findings were available at a shared location for everyone