24 Oct 2013 06:27 AM
    Hello,

    Is there any clear rule set when one can vote 0 during planning for a story ? In the best way I would like to show you the situation: My teammates often want to vote 0 for very simple tasks, but which still are some work to do.
    Telling them "you cannot do so, just because" is not too nice, how would you answer them? Or maybe 0 for simple tasks is nothing bad ?

    Cheers,
    Filip
    Ian Mitchell
    Advanced Member
    Advanced Member
    Posts:571
    Ian Mitchell

    --
    24 Oct 2013 07:41 AM
    Zero what? Zero points, or hours, or something else? Also, are they voting "zero" for the story or one of its tasks? You've used both words here.

    Assuming it is story points, remember that the implemented story has to be peer reviewed and tested. As a minimum a unit test should be put in place, and the work will need to be peer reviewed for conformance with the Definition of Done, and then demonstrated to the Product Owner who presumably sees value in the story the first place. Whether you baseline all of that to a half or 1 is up to you.
    Nitin Khanna
    New Member
    New Member
    Posts:47
    Nitin Khanna

    --
    24 Oct 2013 03:46 PM
    Hi Filip,

    Its nice to see that at least the work is visible. Some teams may not even capture this even though it is considered minimal.

    Are you a member of the Dev Team or the Scrum Master?

    As a Dev Team Member, I think the dialogue is helpful. i.e. "0 because..." or "1 because...."

    As a Scrum Master, there is just facilitation needed to see what makes sense for the Team.

    I would --
    A) Look back to bring some awareness of how much effort it took for a bunch of such Stories / Tasks.
    B) See whether the Team is completing the work forcasted Sprint after Sprint.
    C) Bring awareness to the Definition of Done, agreeing with @Ian to ensure it is robust and includes these items.
    D) [Sneaky] -- Remove the "0" card from my Dev Team members one sprint planning to see what happens.
    ;-)
    Prabhu Missier
    New Member
    New Member
    Posts:26
    Prabhu Missier

    --
    26 Oct 2013 09:53 PM
    Looks like you are alluding to the "Playing Poker" approach. When it comes to sizing I would always recommend using the relative sizing approach so even if you play poker bear that in mind.

    So if your mates want to vote a "0" and assuming they are referring to points or days or hours it implies that they feel its of negligible effort.

    Never fall into the trap of asking your team how many hours or days it going to take. That goes against the Spirit of Scrum. One of the things I tell my team when a similar situation comes up is to keep an open mind and expect change. There have been several cases when a team member has marked a task as trivial only to be surprised when things start unfolding.

    So at the end of the day if the team is pretty sure that its a task with negligible effort then you should probably estimate it at the lowest end of the relative scale you are using.

    Remember no task is a zero effort task if you are a good engineering team. There's always integration testing or documentation or something else to always make it perfect and engineering be short of ways to perfect things.