Skip to main content

How to handle a backlog item where the estimation is extemely off at the end (expect weeks, done in 30 min)

Last post 12:31 am October 18, 2025 by Chris Belknap
3 replies
08:57 pm October 16, 2025

Context 

In my teams, we've been using Planning Poker for over a year now, and it's worked well for what we want to achieve. We use the standard (1, 2, 3, 5, 8, 13...) to estimate each work item before the sprint starts. We  have establish a previous sprints average velocity that we use (for example, 39 points). We then use that average, along with contextual factors (e.g., “John is on vacation this sprint, so let’s aim lower than 39”), to guide what (how many pts) we include in the new sprint initially..

So far, so good. Estimation errors happen occasionally, but they tend to balance out over time ( a  8 might be completed faster, a 3 might take longer. Overall, it averages out enough for our need.)

However, we recently estimated a work item at 8 points (we don’t directly link points to time, but for the sake of argument, let’s say it was perceived as a big week of work, more that one person, etc.). This time, the high estimate was due to uncertainty and the need for research.

But once we started working on it  — boom! A solution was found and applied quickly. Total time: under one hour.

Now, someone on the team rightly pointed out that leaving this item at 8 points will impact our velocity average for several sprints. On the other hand, retroactively adjusting estimates opens a can of worms.

So here’s the question: What’s a good way to handle this kind of situation?  Any suggestions?

I am tempted to « tought it » like that and point out at the next 3-4 sprints that the velocity is slightly high vs reality, since velocity is just a tool... 

 

 


04:07 pm October 17, 2025

You're already taking contextual factors into account, such as your example of someone being on vacation. Why not just remember that there was a significant over (or under) estimation for a couple of Sprints and then move on? You don't need to invest any time in conversations about what the size should have been and can focus on planning your next Sprint.


05:31 pm October 17, 2025

So here’s the question: What’s a good way to handle this kind of situation?  Any suggestions?

Assuming the work is Done, it's already handled. The estimate is over, finished, done with, spent. Learn anything there might be to learn about how to improve future estimation techniques, and move on.


12:31 am October 18, 2025

My teams never adjust past estimates. We keep them as they are, and use the experience to improve how you handle uncertainty in future refinements. Remember, velocity is a guide, not a goal.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.