hi can enyone tell what does burndown charts indicate. how do they help and at who makes it.

02:09 pm June 25, 2013

Burndown charts indicate work left against time.
They should trend downwards, and help the Development Team understand progress. The Development team construct this for the Sprint (hours/day) or release (story points/Sprint).
A good starting point is http://en.wikipedia.org/wiki/Burn_down_chart

10:51 am July 11, 2013

Burndown charts show you the time remaining and is created by the development team itself.