Clarification on Sprint Retrospective

Last post 10:25 am August 19, 2013
by Shirley Santiago
2 replies
Author
Messages
08:51 am August 19, 2013

Hi,

During Sprint Retrospective, is it correct to discuss methods of communication, the way sprint planning is being done and the definition of done?

Thank you.

10:17 am August 19, 2013

Yes on all three counts. Each one of these things is an aspect of how a team has implemented Scrum, and is therefore a valid topic for inspection in a Sprint Retrospective.

10:25 am August 19, 2013

Thank you Ian.