Skip to main content

Due to the Russian invasion of Ukraine, we have paused all purchases and training in and from Russia.

Can we change Sprint Duration after a few initial sprints?

Last post 05:24 am September 15, 2018 by Ian Mitchell
11 replies
05:46 pm December 14, 2016

Hi All,

I wanted to know if after initial few sprints for which lets say we had a duration of 4 weeks, the team decided that we need to increase the duration of the sprint to 5 weeks, is it even an option in SCRUM. We could always adjust the story points for the original sprint duration but my question is to know if it is at all advisable and can be done in SCRUM and who has the final say on it?

Regards,
Krutivas.


06:17 am December 15, 2016

Hi Krutivas,

it is totally OK if the team decides to change the sprint lenght based on "lessions learned", and as a self-organized team they have the final say on it. BUT the maximal duration of the sprint is one month (5 weeks lenght is way too long). If the team feels, that they can't finish their work in 4 weeks, I'm pretty sure, that there is something wrong with the size of the PBIs, they can be decomposed so that they are fitting in a shorter sprint. Most SCRUM teams I know are working with 2 weeks sprint lenght.

Greetings,
Peter


01:02 pm December 15, 2016

Of course it is possible to adjust future sprints length.
Scrum discourage having sprint of > 4 weeks.

What are the reasons the Scrum Team (or Dev Team ?) wants to increase sprint length ?


02:37 pm December 15, 2016

We could always adjust the story points for the original sprint duration

Why would the story points need to be adjusted based on a change to the sprint length? Story points need to reflect the size of a story. They have nothing to do with the size of the iteration.

Per the Scrum Guide, a sprint length must be one month or less (4 weeks or less). It isn't just that a length greater than 4 weeks is discouraged - it is a violation of Scrum.

I also agree with previous comments. It is acceptable to adjust the sprint length based on empirical feedback, but you don't state the reasons that the team wants to increase the sprint length. Keep in mind that adjusting the sprint length should not be done repeatedly, as it harms the team's ability to form a sprint heartbeat, and hurts the ability to form meaningful velocity metrics and thereby impedes the business' ability to plan.


11:15 pm December 15, 2016

Forgive me but there seems to be no way to add a new question to the forums on this site
my question is = Can the sprint backlog be altered during the Sprint

My Answer = yes it can be especially because if the development feels that the scope is more than what they had anticipated or if they are feeling they could add more work from the product backlog they are able to pull work,
Now I happened to be reading - Scrum Master Training Manual for PSM by Nader and Frank where they specifically say that ONCE THE SPRINT BACKLOG IS DEFINED IT CAN NOT CHANGE - Could someone kindly help me decide what the correct answer it?


06:15 am December 16, 2016

This is from the Scrum guide - "The Development Team modifies the Sprint Backlog throughout the Sprint, and
the Sprint Backlog emerges during the Sprint."


04:05 pm December 16, 2016

Now I happened to be reading - Scrum Master Training Manual for PSM by Nader and Frank where they specifically say that ONCE THE SPRINT BACKLOG IS DEFINED IT CAN NOT CHANGE

Ravjote,

If that is what is stated, then the statement is incorrect. As mentioned many times before, be wary of any Scrum "source" other than the Scrum Guide.


05:27 am December 20, 2016

Thanks for the replies everyone.


10:06 am September 14, 2018

The Scrum Guide says: Sprints have consistent durations throughout a development effort....

 

OK... But it also says: 

Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened.

 

The latter suggests that changing the next Sprint lenght in Retrospective is a possibility....

 

So what is the conclusion?


07:07 pm September 14, 2018

You are correct, Kjell. During the retrospective (last event), the team can decide to shorten (to max a week) or to lengthen (to max 4 weeks) the sprint duration. I've done this in the past with several teams. Either as a means to temporarily adapt when there are significant events (ie around Black Friday, Christmas & NY) or as a "permanent" change to reflect the status quo (like moving from 4 to 2 weeks sprint to get to market sooner).

Note that topic doesn't necessarily need to be brought up and decided during the retrospective. Improvement/adapting is a continuous process, so decision to change the sprint length can be taken for example at the end of a refinement session if someone brings it up and there's time to discuss.


05:11 am September 15, 2018

Here are few points from a different perspective (rhythm/pace) to consider change in Sprint Length:

Based on several factors after carefully selecting the Sprint length (max. one calendar month while there is no minimum prescribed as such), you may keep the following under consideration before changing Sprint Length:

#1. Once a sprint length is chosen development team develops a pattern of how to do their work in that particular length of sprint. In other words, a sort of rhythm/pace gets developed/established.

#2. If you change the sprint length after few sprints (for example downwards: 4 weeks to 3 weeks): development team most likely still try to approach the planning with the original sprint length and usually it will result in risk of not being able to deliver the 'done' increment, possibly. And similarly when it is changed upwards (for example: 2 weeks to 3 weeks) there is again a risk of delivering less, possibly.

#3. So whenever you change the sprint length, you need to note that once again it will take few sprints for the rhythm/pace to get developed/established again.

 


05:24 am September 15, 2018

Note that topic doesn't necessarily need to be brought up and decided during the retrospective. Improvement/adapting is a continuous process, so decision to change the sprint length can be taken for example at the end of a refinement session if someone brings it up and there's time to discuss.

Yes, bearing in mind that it is of course the length of future sprints which is being negotiated.

Note that the Scrum Team should reconsider the matter of revising Sprint length during the Retrospective, even if it has been discussed thoroughly beforehand. The actual decision should be made just-in-time on the basis of the latest information available.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.