    Hi,

    During Sprint Retrospective, is it correct to discuss methods of communication, the way sprint planning is being done and the definition of done?

    Thank you.
    Ian Mitchell
    Advanced Member
    Advanced Member
    Posts:570
    Ian Mitchell

    --
    19 Aug 2013 09:17 AM
    Yes on all three counts. Each one of these things is an aspect of how a team has implemented Scrum, and is therefore a valid topic for inspection in a Sprint Retrospective.
    SSantiago
    New Member
    New Member
    Posts:7
    SSantiago

    --
    19 Aug 2013 09:25 AM
    Thank you Ian.