Sprint 0...or not?
Last Post 07 Jul 2014 03:37 PM by Srinivas R Nutalapati. 5 Replies.
  •  
  •  
  •  
  •  
  •  
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Author Messages
Sabur Malik
New Member
New Member
Posts:1
Sabur Malik

--
30 Jun 2014 07:08 AM
    HI -

    I just sat the PSM I and came across a question related to Sprint 0 - a concept that doesn't feature in 'The Definitive Guide to Scrum: The Rules of the Game'.

    Is Sprint 0 a recognized concept for the purposes of the PSM I test?

    Thanks

    S
    Ian Mitchell
    Veteran Member
    Veteran Member
    Posts:1451
    Ian Mitchell

    --
    30 Jun 2014 07:18 AM
    No, it isn't. See these threads for more information:

    https://www.scrum.org/Forums/aft/645
    https://www.scrum.org/Forums/aft/366
    Abhishek Bhatia
    New Member
    New Member
    Posts:1
    Abhishek Bhatia

    --
    01 Jul 2014 01:54 AM
    From SCRUM timeboxed events perspective, it is not a valid sprint. It is usually the name given to do initial activities like refining product backlog, architecture envisioning, priortization and release planning etc.
    Joshua Partogi
    Basic Member
    Basic Member
    Posts:107
    Joshua Partogi

    --
    02 Jul 2014 11:05 AM
    Yes it is if you are using Zero-based numbering like in C like language.

    If you are using VB then it starts with 1.
    Ian Mitchell
    Veteran Member
    Veteran Member
    Posts:1451
    Ian Mitchell

    --
    03 Jul 2014 04:00 AM
    > From SCRUM timeboxed events perspective,
    > it is not a valid sprint. It is usually the name
    > given to do initial activities like refining
    > product backlog, architecture envisioning,
    > priortization and release planning etc.

    True. However just to be clear, it isn't the nature of these activities which make the "Sprint Zero" concept invalid. The problem is that it does not usually result in an increment which the Product Owner values, nor is it usually timeboxed for that purpose.

    It could be argued that a PO *should* value the things you mention, and that readying the Scrum instance is a meaningful goal for the first sprint.
    Srinivas R Nutalapati
    New Member
    New Member
    Posts:2
    Srinivas R Nutalapati

    --
    07 Jul 2014 03:37 PM

    From official scrum guide - there is no Sprint 0.

    In practical world, when a team sets out to adopt Scrum - usually Sprint 0 is used for the first time to adopt the scrum framework in the current business process.

    Sprint 0 - as any other sprint - has a goal. The goal usually is to set the team for a change. The goal is agreed by the scrum team. One of the basic requirement of the scrum is to have a product backlog and this sprint 0 is ideal to solidify the approach to maintain the backlog either in Agile software tools/Wiki or shared project notebook or post it notes on the wall. or select another that simplifies the work.

    Sprint 0 - may or may not have a potentially ship-able product increment - agreed by the scrum team.

    http://www.mountaingoatsoftware.com...dea-or-not