can we have stories in sprint without assignee

Last post 02:06 pm August 10, 2020 by Curtis Slough
4 replies
04:06 pm August 6, 2020

Hello

I have a basic question. When sprint starts, is it mandatory to have all the stories that are part of the sprint should be assigned to a resource?

 


09:56 pm August 6, 2020

When sprint starts, is it mandatory to have all the stories that are part of the sprint should be assigned to a resource?

Naveen Hks, In my opinion, No, the PBI's are converted to a Done Increment by the Development Team. How they decide to accomplish this as a "team" is upto them. This is how they self-organize.


10:05 pm August 6, 2020

There are a few things to keep in mind:

  • Scrum does not require "stories". Although User Stories are a common representation for Product Backlog Items, they are not the only way. Even if User Stories are used for some Product Backlog Items, some work may not be best suited to this style and alternative formats are used.
  • Scrum does not require assigning Product Backlog Items or Sprint Backlog Items to anyone at any point in time. Some teams may find this useful to understand who is the primary person working on something. Some teams may assign to a group instead, such as a pair. Sometimes, tools may enforce that a person is assigned to each work item. None of this comes from Scrum, though.
  • It's best to not refer to people as "resources". People are people. When you refer to people as resources, you often start to see them as more interchangeable than they really are. People have unique backgrounds, knowledge, and skill sets that allow them to contribute to the team and organization.

02:51 am August 7, 2020

I have a basic question. When sprint starts, is it mandatory to have all the stories that are part of the sprint should be assigned to a resource?

When a Sprint starts, it might be reasonable to then start Sprint Planning. What does the Scrum Guide say about this event? What conclusions can you draw about "stories", the "assignation" of work to so-called "resources", and what is and is not "mandatory"?


02:06 pm August 10, 2020

Scrum has nothing to say about stories or how they are used. 

Practically, in my teams the story is never assigned to a single person because the team owns these. The tasks we do have an "assignee" but it's just designating the team member who picked up that individual task; no one is directing the team to take a particular task.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.