Sprint Duration Question
Last post 11:42 am July 27, 2015
by Ching-Pei Li
3
replies
05:34 am July 24, 2015
When we say a for example a two week sprint, is the sprint planning, sprint review and sprint retrospective come inside those two weeks
Regards
Raja
06:19 pm July 24, 2015
Yes.
A sprint begin at sprint planning, and end at sprint retrospective.
11:26 am July 27, 2015
Yes.
A good way to look at it is that the Sprint is the timeboxed event that contains all the other timeboxed events.
Don
11:42 am July 27, 2015
Don's answer is much better than mine.
A time-boxed container concept is more suitable than an 1-D timeline which forces on begin-end.